St. Mary of the Lake - North Addition
While the St. Mary of the Lake –
North Addition project was small, it presented many challenges along
the way. We were contracted to create a new Day Chapel on the raised
alter in the existing Sanctuary.
(See Existing Sanctuary
Photo) This involved opening the back wall of the alter, creating
a vestibule and second entrance. The entrance provide a covered
drop off area with stairs to the new doors. Handicap accessibility
was achieved through the installation of a serpentine ramp adjacent
to the stairs. Separation of the Day Chapel from the existing Sanctuary
was achieved by creating a dividing glass wall. As part of this
project, the existing 1950's boilers were removed and replaced with
new high efficiency boilers and with zoned controls to take advantage
of the newly segregated space. All of this had to be achieved while
keeping the existing Sanctuary operational, clean and conducive
to worship.
This existing Sanctuary has wood trim stained to allow the grain
to show through and add a richness to the space. Kelty Tappy Design,
Inc., the design Architect, determined that the dividing glass wall
should continue this theme. The size of the wall and the glass panels
used made a wood framed structure impossible so it was determined
that a steel framed structure would be required. This steel structure
would then need to be covered with wood.
The dividing glass wall was designed with a symmetrical geometric
design. Unfortunately the existing sanctuary walls and ceiling were
far from symmetrical. The walls were not plumb causing the ceiling
angles and lengths to differ. Following careful field measurements
of the existing conditions, multiple reiterations of the design
were adjusted until a layout was found that balanced the new wall
geometry with the existing structural flaws.
While we were working with the Architect to determine the final
layout, we were also working with our metal fabricator to determine
the best way to segment the structure so that it could be brought
into the new space through a standard double door opening. Because
of the wood covering it was decided that all of the connections
would be welded to minimize issues with covering the framework with
wood. This further complicated the installation as it was not possible
to completely check the fit on the ground. There were also issues
with the inherent weight of the members. It was necessary to check
all the angles and brace the entire structure in place prior to
welding to assure no spreading occurred between members.
 |
| Welding
of the Glass Dividing Wall Framework
(Click
to see Larger Image) |
The welding process presented
even more challenges. The structure had to be welded together high
above the existing Sanctuary alter. Since the alter was in use throughout
the week for various services it was not possible to completely
remove things. We had to protect the sanctuary during the welding
operation as we did throughout construction. (See Welding of
Glass Dividing Wall Framework Photo)
We used two scissor lifts in order to access both sides of the wall
throughout construction. The newly created doors between the Day
Chapel and the existing sanctuary were narrow, requiring partial
disassembly of the lift in order to go through the doors. This meant
our lift was on the alter through several worship services variously
shrouded or screened so as not to distract from the ceremony. Due
to the intricate carpentry required to cover the steel and prepare
for the installation of glass, thissituatio n was coordinated between
the pastor and our site superintendent. (See Wood Trim Application
to the Steel Framework Photo)
The majority of the glass
installed was planned to be clear. This did not allow any separation
or screening for our work areas. It as also determined that a local
artist would provide etched glass artwork depicting St. Mary rising
above the Lake on the central, focal glass section. The artist had
not previously worked in this medium, so again, multiple trials
were necessary to adapt the proposed artwork to the stark positive/negative
medium of etched glass.
| The final product far exceeded
expectations and the Church has been extremely pleased with
their new Day Chapel and the enhancements to the Sanctuary.
|
The final product far
exceeded expectations and the Church has been extremely pleased
with their new Day Chapel and the enhancements to the Sanctuary.
(See Completed Sanctuary Photo) They were able to observe
the work as it proceeded weekly and were able to take some ownership
in the project as it progressed. This was a far different situation
than when the congregation is does not witness the construction
and only sees the final product when it is revealed in a dedication
ceremony.
On the outside, the entrance work provided it's own challenges.
St. Mary of the Lake has an active Day Care Facility. While safety
is always an issue for construction sites, extra care was taken
to make sure there were clearly marked and segregated boundaries
to prevent children traveling to and from the Day Care Facility
from venturing into the site. The site was quite tight, so much
of the work was completed in the adjacent street further complicating
this issue. As with any renovation of this type, “Sidewalk
Superintendents” took an active interest and provided constant
advice as the project moved forward.
Brick were not available
to match the existing structure, so care was taken to find a compatible
mix that enhanced the existing building. A concealed lintel was
specified that allowed a sweeping arch of brick with no visible
support.
This was a new product
for our masons and a learning experience. Fortunately instructions
were clear and they were able to complete this installation with
minimal difficulty.
Two shorter spanned openings
were constructed on either side of the arch using the same concealed
lintel, but without any arch. The effect has left many patrons and
more than a few contractors scratching their heads and wondering
what is holding the brick in place. (See Concealed Brick Lintel
Photo)
The final challenge on this project was that this was a bid project
for a renovations to a small town Church. The budget was limited
and as with any modification to an existing facility, unforeseen
problems were uncovered in the existing structure. We worked closely
with the Architect, Engineer and St. Mary of the Lake to find solutions
that were creative and affordable. Despite these issues, we were
able to bring the project to completion within the budget.
|